HiSkin launch timeline
Contracts signed by Monday
pending client signaturePre-kickoff
Phase 1 Discovery starts immediately after contract execution
ready after signatureWeek 1
Studio manager training: first week of June
not startedFirst week of June 2026
Studio team training starts: June 15
not startedJune 15, 2026
Full launch: July 1
launch deadline fixedJuly 1, 2026
Ongoing coaching begins after rollout / immediately post-launch
retainer pendingPost-launch
Timeline risks
- July 1 launch deadline is fixed and creates schedule pressure.
- Discovery and build/deploy must complete before launch readiness.
- Data, access, device readiness, and approval owners are launch-gating dependencies.
Project Delivery → Schedule
Gantt schedule · HiSkin Membership Sales System Implementation
Project-scoped phases, dependencies, owners, windows, and status. This chart does not imply work has started.
Enterprise onboarding, NDA, intake, access path
HiSkin / Ariel
Conversion baseline, membership assumptions, system/source map
Ariel West Long
Scripts, objection guide, follow-up templates, KPI scorecard
Ariel West Long
RAMP checkpoints, manager coaching, QA review path
Shared
Launch readiness approval, rollout support, handoff criteria
Shared
| Phase | Task | Owner | Window | Status | Dependencies |
|---|---|---|---|---|---|
| Phase 1: Intake + Access Readiness | Enterprise onboarding, NDA, intake, access path | HiSkin / Ariel | Pre-kickoff → Kickoff | pending client | Primary decision maker confirmed |
| Phase 2: Baseline + System Mapping | Conversion baseline, membership assumptions, system/source map | Ariel West Long | Kickoff → Week 1 | pending client | Intake + access readiness |
| Phase 3: Sales Rollout Build | Scripts, objection guide, follow-up templates, KPI scorecard | Ariel West Long | Weeks 2 → Weeks 4 | not started | Baseline + system mapping |
| Phase 4: Training + QA Readiness | RAMP checkpoints, manager coaching, QA review path | Shared | Month 2 → Month 2 | not started | Sales rollout build |
| Phase 5: Launch + Stabilization | Launch readiness approval, rollout support, handoff criteria | Shared | Month 2+ → Month 3 | not started | Training + QA readiness |
Project Delivery → Critical Path
Launch-gating critical path · HiSkin Membership Sales System Implementation
Items below gate project launch and map back to onboarding phases, schedule items, and launch readiness.
pending client · medium risk
Enterprise onboarding completed
Submit onboarding and stakeholder details.
Next action: Complete the delivery onboarding console.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: phase-1-enterprise-onboarding
Schedule item: phase-1-enterprise-onboarding
Dependencies: phase-1-enterprise-onboarding
pending client · medium risk
NDA / intake confirmed
NDA acknowledgement and intake are required before kickoff.
Next action: Submit NDA acknowledgement.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: enterprise-onboarding-completed
Schedule item: enterprise-onboarding-completed
Dependencies: enterprise-onboarding-completed
pending client · high risk
Primary decision maker confirmed
Project decisions need a named owner.
Next action: Confirm Shannon/Mark approval path.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: nda-intake-confirmed
Schedule item: nda-intake-confirmed
Dependencies: nda-intake-confirmed
pending client · high risk
Approval process confirmed
Delivery review can stall without a clear approval model.
Next action: Confirm approvers and turnaround expectations.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: primary-decision-maker-confirmed
Schedule item: primary-decision-maker-confirmed
Dependencies: primary-decision-maker-confirmed
pending client · medium risk
Location list confirmed
Location scope must stay source-visible.
Next action: Confirm all 9 locations and any exclusions.
Owner: HiSkin
Due: Kickoff
Onboarding phase: enterprise-onboarding-completed
Schedule item: enterprise-onboarding-completed
Dependencies: enterprise-onboarding-completed
pending client · high risk
Baseline conversion data confirmed
Current conversion remains an assumption until confirmed.
Next action: Provide confirmed baseline source or export path.
Owner: HiSkin
Due: Week 1
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
pending client · high risk
Boulevard access/readiness confirmed
Boulevard is not connected in demo mode.
Next action: Confirm export owner and report list.
Owner: HiSkin
Due: Week 1
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
pending client · medium risk
Absorb access/readiness confirmed
Absorb outline is needed for training alignment.
Next action: Confirm training outline source.
Owner: HiSkin
Due: Week 1
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
not started · medium risk
Training content path confirmed
Training path must be confirmed before QA readiness.
Next action: Map RAMP and manager checkpoints.
Owner: Shared
Due: Weeks 2-4
Onboarding phase: sales-rollout-build
Schedule item: sales-rollout-build
Dependencies: sales-rollout-build
pending client · high risk
Membership offer / pricing assumptions confirmed
$119/month terms are pending client confirmation.
Next action: Confirm membership price, perks, and service inclusion.
Owner: HiSkin
Due: Kickoff
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
not started · medium risk
QA review path confirmed
QA path is required before launch readiness.
Next action: Confirm review evidence and owner.
Owner: Shared
Due: Month 2
Onboarding phase: training-qa-readiness
Schedule item: training-qa-readiness
Dependencies: training-qa-readiness
not started · high risk
Launch readiness approval confirmed
Launch cannot proceed without explicit approval.
Next action: Confirm launch approval owner and criteria.
Owner: HiSkin
Due: Month 2
Onboarding phase: training-qa-readiness
Schedule item: training-qa-readiness
Dependencies: training-qa-readiness
Timeline / next milestones
Activation
Contract signed by Monday
Owner: Shannon · Target: Monday · active
Phase 1 - Discovery
Phase 1 Discovery starts immediately after contract execution
Owner: Ariel West Long · Target: Week 1 · not started
Phase 2 - Build & Deploy
Studio manager training
Owner: Taylor Duncan / Ariel · Target: First week of June · not started
Training
Studio team training starts
Owner: Taylor Duncan · Target: June 15 · not started
Launch Readiness
Full launch
Owner: Shannon / Ariel · Target: July 1 · not started
Ongoing Retainer
Ongoing coaching begins after rollout
Owner: Ariel West Long · Target: Post-launch · not started