Project Delivery · HiSkin Membership Sales System Implementation
MemberLift → HiSkin Membership Sales System Implementation → Project Delivery. This workspace is scoped to HiSkin onboarding, launch readiness, RFIs, meetings, Slack, Close sync previews, and semi-automated delivery operations only.
Project Delivery → Critical Path
Launch-gating critical path · HiSkin Membership Sales System Implementation
Items below gate project launch and map back to onboarding phases, schedule items, and launch readiness.
pending client · medium risk
Enterprise onboarding completed
Submit onboarding and stakeholder details.
Next action: Complete the delivery onboarding console.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: phase-1-enterprise-onboarding
Schedule item: phase-1-enterprise-onboarding
Dependencies: phase-1-enterprise-onboarding
pending client · medium risk
NDA / intake confirmed
NDA acknowledgement and intake are required before kickoff.
Next action: Submit NDA acknowledgement.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: enterprise-onboarding-completed
Schedule item: enterprise-onboarding-completed
Dependencies: enterprise-onboarding-completed
pending client · high risk
Primary decision maker confirmed
Project decisions need a named owner.
Next action: Confirm Shannon/Mark approval path.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: nda-intake-confirmed
Schedule item: nda-intake-confirmed
Dependencies: nda-intake-confirmed
pending client · high risk
Approval process confirmed
Delivery review can stall without a clear approval model.
Next action: Confirm approvers and turnaround expectations.
Owner: HiSkin
Due: Pre-kickoff
Onboarding phase: primary-decision-maker-confirmed
Schedule item: primary-decision-maker-confirmed
Dependencies: primary-decision-maker-confirmed
pending client · medium risk
Location list confirmed
Location scope must stay source-visible.
Next action: Confirm all 9 locations and any exclusions.
Owner: HiSkin
Due: Kickoff
Onboarding phase: enterprise-onboarding-completed
Schedule item: enterprise-onboarding-completed
Dependencies: enterprise-onboarding-completed
pending client · high risk
Baseline conversion data confirmed
Current conversion remains an assumption until confirmed.
Next action: Provide confirmed baseline source or export path.
Owner: HiSkin
Due: Week 1
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
pending client · high risk
Boulevard access/readiness confirmed
Boulevard is not connected in demo mode.
Next action: Confirm export owner and report list.
Owner: HiSkin
Due: Week 1
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
pending client · medium risk
Absorb access/readiness confirmed
Absorb outline is needed for training alignment.
Next action: Confirm training outline source.
Owner: HiSkin
Due: Week 1
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
not started · medium risk
Training content path confirmed
Training path must be confirmed before QA readiness.
Next action: Map RAMP and manager checkpoints.
Owner: Shared
Due: Weeks 2-4
Onboarding phase: sales-rollout-build
Schedule item: sales-rollout-build
Dependencies: sales-rollout-build
pending client · high risk
Membership offer / pricing assumptions confirmed
$119/month terms are pending client confirmation.
Next action: Confirm membership price, perks, and service inclusion.
Owner: HiSkin
Due: Kickoff
Onboarding phase: baseline-system-mapping
Schedule item: baseline-system-mapping
Dependencies: baseline-system-mapping
not started · medium risk
QA review path confirmed
QA path is required before launch readiness.
Next action: Confirm review evidence and owner.
Owner: Shared
Due: Month 2
Onboarding phase: training-qa-readiness
Schedule item: training-qa-readiness
Dependencies: training-qa-readiness
not started · high risk
Launch readiness approval confirmed
Launch cannot proceed without explicit approval.
Next action: Confirm launch approval owner and criteria.
Owner: HiSkin
Due: Month 2
Onboarding phase: training-qa-readiness
Schedule item: training-qa-readiness
Dependencies: training-qa-readiness
Dependencies
NDA / intake confirmed
pending client · medium riskNDA and intake are not confirmed yet.
Owner: HiSkin · Required by: Pre-kickoff · Next: Complete nested Project Delivery onboarding.
Location list confirmed
pending client · medium risk9-location structure exists, but locations beyond HTX are placeholders.
Owner: HiSkin · Required by: Kickoff · Next: Confirm location names and owners.
Boulevard access/readiness confirmed
pending client · high riskBoulevard is not connected in demo mode.
Owner: HiSkin · Required by: Week 1 · Next: Confirm export/report owner.
Membership offer / pricing assumptions confirmed
pending client · high risk$119/month terms remain ASSUMPTION_PENDING_CLIENT_CONFIRMATION.
Owner: HiSkin · Required by: Kickoff · Next: Confirm membership price, discounts, B12, and monthly service inclusion.